The King’s Cross Energy Centre and Primary Electrical Substation shell works are now complete, and the six month fit-out of plant by the various utility contractors involved in the project is now well progressed. On completion, the works will constitute the first step in a planned phased installation of plant to serve the development as it grows. Kier will remain in place as Principal Contractor for the duration of the first phase of works.
Installation of below ground utilities in the Eastern Goods Yard is almost complete and the final connection to the Energy Centre is being made in preparation for the commissioning works to the UAL campus during the third quarter of 2010.